Client: British Columbia Hydro and Power Authority (BC Hydro)
Project Location: British Columbia, Canada
Main Discipline: Electrical Transmission
Year: 2021 – present
A seven-year program for transmission asset upgrades including end-of-life conductor replacement, line upgrades and relocations, pole and disconnect switch replacements, cross-arm replacements, and clearance mitigation design. The engineering services provided by Kosmos Group include field verification and data collection, scoping, detailed design, issuing of IFC packages, construction support, and As-Built close-out. Our design team also coordinates and works with 3rd party stakeholders (local government, highways, and pipeline companies) to confirm design viability.